Bear Creek Trail Progress Update

Progress update on the Bear Creek Trail construction occurring between S. Estes St. and S. Kipling Pkwy:

  • The long duration of the Phase 4 detour is due to the structural work at the Estes St. underpass and the replacement of the “Beaver Dam” or “90-degree” bridge between Estes and Kipling. The safety improvements under Estes include realignment of the trail approaches to improve trail slope, width and sightlines. This change requires new walls at the edge of the creek and storm drain extensions on both sides of Estes.
  • The new bridge in this reach will span the creek at a lesser angle to soften the approach curves to improve safety. The bridge will feature mid-span “outlookers” to allow users to get off the trail and enjoy the view or snap some Instagram pics.
  • A new, natural surface trail loop, south of the main trail, will provide access to a new addition to the greenbelt, providing an elevated view of the valley above the 90-degree bridge.

Share Bear Creek Trail Progress Update on Facebook Share Bear Creek Trail Progress Update on Twitter Share Bear Creek Trail Progress Update on Linkedin Email Bear Creek Trail Progress Update link
<span class="translation_missing" title="translation missing: en-US.projects.blog_posts.show.load_comment_text">Load Comment Text</span>